NLMK USA is taking an unplanned seven- to 10-day outage on the hot-strip mill at its facility in Farrell, Pa., a company executive said.
The repairs are necessary because a motor failed on the reversing roughing mill, NLMK USA Executive Vice President James Banker told Steel Market Update on Tuesday, May 11.
The company will therefore pull forward planned maintenance on the hot-strip mill that had been scheduled for June. The repairs will result in hot-rolled coil orders being delayed by approximately two weeks, he said.
“We’ll be caught up by June. And we’ll be prioritizing orders that are affected by this outage,” Banker said.
Shipments of downstream pickled-and-oiled (P&O), cold-rolled and coated products should not be impacted because those lines already had work-in-process inventory on hand, he said.
While the June outage on the hot-strip mill has been pulled forward, planned outages on downstream operations remain scheduled for July, Banker said.
The Farrell mill, like NLMK’s electric-arc furnace (EAF) steel mill in Portage, Ind., typically takes one week of downtime for major planned maintenance every six months, he noted.
Also known as NLMK Pennsylvania, the Farrell mill is the company’s largest plant in the U.S. Farrell’s hot-strip mill has annual capacity of 1.8 million tons, according to the Association for Iron and Steel Technology’s 2021 Directory of Iron and Steel plants. NLMK USA sells hot-rolled coil, hot-rolled P&O, cold-rolled coil, and galvanized products to service centers as well as a range of end-use markets, including HVAC, appliance, and pipe and tube.
NLMK’s Sharon Coating facility, located in nearby Sharon, Pa., makes galvanized and galvannealed products.
By Michael Cowden, Michael@SteelMarketUpdate.com
Michael Cowden
Read more from Michael CowdenLatest in Steel Mills
BREAKING NEWS: Cliffs moves sheet prices up by $60/st, seeks $900/st HRC
Cleveland-Cliffs aims to increase sheet prices by $60 per short ton (st) and is seeking a new target base for hot-rolled coil (HRC) of $900/st. That's according to a press release circulated on Wednesday morning, March 27.
SSAB could use DOE funding to expand US operations
With the help of a large government grant, SSAB may soon expand its operations in the US – including constructing a fossil-fuel-free green ironmaking facility in Mississippi.
Iron, steel win big in Dept. of Energy’s $6B decarb initiative
The Department of Energy (DOE) announced on Monday six projects that will receive up to $1.5 billion in funding to further decarbonize the iron and steel industry.
Cliffs to use DOE grant to replace Middletown BF with DRI, EMF plant
Cleveland-Cliffs Inc. has plans to replace the blast furnace at its Middletown Works in Ohio with a direct-reduced iron (DRI) plant and two electric melting furnaces (EMFs).
CMC’s Arizona 2 micro-mill shifts focus on West Coast rebar glut
A temporary surplus of rebar on the West Coast is forcing CMC to alter the planned ramp-up of its Arizona 2 micro-mill, the company's leader said on Thursday.