Steel Mill Lead Times Moving Out
Written by John Packard
March 23, 2017
Flat rolled lead times, which had been stuck in a rut over the past couple of months, have started to move out according to those responding to our flat rolled market trends survey. We are now seeing average lead times on hot rolled close to five weeks (4.81 weeks). We also saw movement in cold rolled, galvanized and Galvalume lead times.
Lead time is the amount of time, referenced in weeks, that it takes a new order to be produced by the domestic steel mills.
In the case of hot rolled, lead times had been averaging less than 4.5 weeks but that changed this week as our survey respondents reported the average as being closer to 5 weeks (4.81 weeks). This is almost one week longer than what we saw in the middle of March 2016.
Cold rolled lead times are also moving out (extending) and are closing in on 7 weeks (6.85 weeks). One year ago CR lead times were reported to be averaging 6.60 weeks.
Galvanized lead times move out and are now being reported as averaging slightly more than 7 weeks (7.13 weeks). This is in-line with the 7.29 weeks reported for GI last year at this time.
Galvalume lead times moved out the furthest from 6.93 weeks at the beginning of March to 7.62 weeks this week. One year ago AZ lead times averaged 6.60 weeks.
We remind our readers that the lead times referenced in this article have nothing to do with the lead times being quoted by individual steel mills. Our lead times are based on an average of the responses to our flat rolled steel market trends survey. We recommend that buyers speak with their suppliers to get the exact lead times for your products.
A side note: The data for both lead times and negotiations comes from only service center and manufacturer respondents. We do not include commentary from the steel mills, trading companies, or toll processors in this particular group of questions.
To see an interactive history of our Steel Mill Negotiations data, visit our website here.
John Packard
Read more from John PackardLatest in SMU Data and Models
Steelmaking raw material prices mixed in April
Prices of steelmaking raw materials have moved in different directions over the last 30 days, according to Steel Market Update’s latest analysis.
March service center shipments and inventories report
Flat Rolled = 58.3 shipping days of supply Plate = 60.6 shipping days of supply Flat Rolled US service center flat-rolled steel inventories edged up in March as shipments remained low. At the end of March, service centers carried 58.3 shipping days of supply on an adjusted basis, up from 56.6 shipping days in February. […]
SMU survey: Buyers’ sentiment increases
SMU’s Steel Buyers’ Sentiment Indices both rose this week.
SMU market survey results now available
The latest SMU market survey results are now available on our website to all premium members. After logging in at steelmarketupdate.com, visit the pricing and analysis tab and look under the “survey results” section for “latest survey results.” Historical survey results are also available under that selection. If you need help accessing the survey results, or if […]
SMU survey: Sheet lead times contract, plate pushes out
The market appears to be taking a pause after the heavy buying that occurred in March.