ArcelorMittal Calvert electrical steel mill remains on track for 2027 start
ArcelorMittal Calvert is progressing on the construction of its new $1.2-billion non-grain-oriented electrical steel (NGO or NOES) mill, with production slated to begin in 2027. The steelmaker reported in its third-quarter earnings that it's on track with the 150,000-metric-ton-per-year project, located adjacent to its existing sheet mill in Calvert, Ala. In a Nov. 11 stakeholder newsletter, ArcelorMittal said the electrical steel production lines are taking shape: an annealing and pickling line on the west side of the mill and an annealing and coating line on the east side.