Phase 2 of Algoma Plate Mill Upgrades Pushed to June 2023
Written by Michael Cowden
August 9, 2022
Algoma’s plate mill is up and running following the first phase of a modernization project that was completed in June.
The second phase of the expansion, initially expected to be finished by November 2022, has been moved to June 2023, a company spokeswoman told SMU on Tuesday, Aug. 9.
The reason: “to support our customers impacted by a longer-than-anticipated outage due to automation issues during the first phase,” she said.
Algoma had scheduled a one-month outage in its fiscal first quarter, which ended in June, to complete the first phase of upgrades. It took the steelmaker approximately six to eight weeks longer than expected to start up the mill following the outage, company executives said on an earnings conference call with analysts last week.
The protracted start-up resulted from problems with automation equipment installed as part of the upgrades. The result: Production and shipment volumes in both the first and second quarters of Algoma’s fiscal year are expected to be lower than in the same quarters last year, they said.
Algoma makes hot-rolled coil, cold-rolled coil, and plate. Company executives noted that the outage and delayed start-up of the plate mill would impact not only discrete plate volumes but also those of strip mill plate too.
SMU’s plate price averaged $1,735 per ton ($86.75 per cwt) when this article was filed, down 3.6% from $1,800 per ton a month earlier on the heels of a price decrease announced by Charlotte, N.C.-based Nucor Corp.
By Michael Cowden, Michael@SteelMarketUpdate.com

Michael Cowden
Read more from Michael CowdenLatest in Steel Mills

August US mill shipments slip but still higher than last year
The American Iron and Steel Institute reported a decline in the monthly shipments of US mills from July to August.

TransPod, Algoma, Supreme Steel linkup anchors Canadian steel in high-speed transit build
The three Canadian companies have announced a strategic partnership to support the development of an ultra-high-speed transit line from Edmonton to Calgary.

Metallus, USW agree to tentative four-year labor deal
Metallus and the United Steelworkers (USW) have agreed to a tentative four-year labor contract.

ArcelorMittal Dofasco resumes cokemaking after emergency maintenance
The Canadian steelmaker reported on Sept. 30 that “urgent maintenance” was needed in its coke plant off-gas systems. The work required coke oven gas from the No. 2 coke plant to be flared for most of that week.

AISI: Raw steel production ticks back down
US raw steel output declined last week after increasing the week prior, according to the latest data from the American Iron and Steel Institute (AISI). Output has see-sawed from week to week since mid-August. Still, it has remained historically strong over the past four months and has held near multi-year highs since June. Domestic mills […]