October 10, 2024
SMU survey: Mill lead times stretch out marginally
Written by Brett Linton
Steel mill lead times inched up this week for most sheet and plate products, according to buyers responding to our latest market survey. Compared to late-September, lead times have marginally extended for all products other than galvanized. Overall, lead times remain near some of the shortest levels witnessed this year.
Production times are mixed this week compared to those seen one month prior, but higher for all products vs. levels three months ago. For sheet products, lead times for hot-rolled steel remain around five weeks on average and tandem products are all hovering around seven weeks. Plate lead times continue to register about four weeks, around where they have been since mid-July.