US Steel Idles Gary Works No. 8 BF on Market Conditions, High Imports
Written by Laura Miller
September 15, 2022
United States Steel Corporation has idled the No. 8 blast furnace at its Gary Works in Indiana due to market conditions and high import levels.
A spokeswoman confirmed the idling began on Sept. 7.
“We continue to monitor market conditions and plan to bring the furnace back online when business conditions allow,” she told SMU.
No job losses are taking place as a result of the furnace’s idling, with all employees being reassigned to other areas of Gary Works, she said.
SMU’s blast furnace status table has been updated to reflect the idling.
Gary Works is US Steel’s largest steelmaking complex with an annual raw steel capacity of 7.5 million tons of hot-rolled, cold-rolled and coated sheet – including tin mill products. The No. 8 BF has a daily capacity of 3,000 tons of pig iron.
Weaker demand and increased imports were also blamed for the temporary idling of the No. 5 tin line at Gary Works earlier this month.
A month-long outage is also currently underway at the steelmaker’s No. 3 Mon Valley Works blast furnace near Pittsburgh. That planned maintenance outage—to apply shotcrete—was pulled forward from its originally-scheduled date of mid-October.
US Steel released third quarter earnings guidance this week, saying it expects Q3 EBITDA of $825 million to be down nearly 50% sequentially and down 60% from the year-ago quarter. Accelerating market headwinds, including weaker demand, lower shipments, and lower selling prices are the reasoning for the anticipated lower earnings.
Negotiations for a new labor contract between the steelmaker and the United Steelworkers union continue, with wage increases remaining a major area of contention, according to a Sept. 9 USW bargaining update.
By Laura Miller, Laura@SteelMarketUpdate.com

Laura Miller
Read more from Laura MillerLatest in Steel Mills

USW seeks clarity on plans for Granite City Works
The United Steelworkers union has asked U.S. Steel to elaborate on its Granite City Works plans following reports that the steelmaker is ending processing at the facility.

Nucor maintains plate prices, opens October order book
Nucor aims to keep plate prices flat for a seventh straight month with the opening of its October order book.

ArcelorMittal Mexico to import from sister mills as it works to resume DRI production
ArcelorMittal has partially restarted operations at its direct reduction plant in Lazaro Cardenas, Michoacan. An explosion on Aug. 18 rocked the massive steelworks on Mexico’s Pacific coast, impacting production of direct-reduced iron (DRI).

Fall maintenance outages are coming in hot
Labor Day has passed, the sun is starting to set a little earlier each day, and cooler weather has begun to find its way down to many of us across North America. And you know what that means for the steel industry… Fall maintenance outages!

AISI: Domestic steel production ticks up
US raw steel production ticked up in the week ending on Sept. 6 after a decrease the week before, according to the most recent data from the American Iron and Steel Institute (AISI).