USS Pulls Ahead Planned Maintenance on Mon Valley Blast Furnace
Written by Michael Cowden
July 21, 2022
US Steel plans to take an approximately one-month outage in September on the No. 3 blast furnace at is Mon Valley Works near Pittsburgh, a company spokeswoman said.
The steelmaker plans to apply shotcrete – sprayed concrete – to the furnace, she added.
Shotcrete is a significantly shorter and less expensive process than a full reline.
The work was originally scheduled for mid-October.
Mon Valley Works has two blast furnaces: No. 1 and No. 3. The No. 1 furnace has daily ironmaking capacity of approximately 3,200 tons. The No. 3 furnace has daily capacity of approximately 2,900 tons.
The furnaces are located at US Steel’s Edgar Thomson plant in Braddock, Pa. That facility makes slabs and rails them to the company’s Irvin Plant in West Mifflin, Pa., where they are rolled into sheet.
SMU has updated its blast furnace status table, found by clicking here, to reflect the development.
By Michel Cowden, Michael@SteelMarketUpdate.com

Michael Cowden
Read more from Michael CowdenLatest in Steel Mills

Op-Ed: Ternium CEO Máximo Vedoya wants a fair future forged in steel
After recently receiving an industry honor on behalf of Ternium, I had the opportunity to reflect and share my vision on the state and future of our industry.

Nippon eyeing new $4B U.S. Steel mill to sweeten deal: Report
Nippon Steel could build a new domestic U.S. Steel mill with a total investment of $4 billion.

Nucor cuts CSP by $20/ton, third straight drop
Nucor has lowered its consumer spot price by $20 per short ton, marking the third consecutive weekly decrease.

Nucor reports IT systems breach
Nucor said it temporarily and proactively halted some production operations at various locations.

Cliffs talks DOE funding, blast furnace relining schedule
The future of two projects supported in part by funding through the Department of Energy remains uncertain.