USS's Mon Valley No. 3 BF Could Stay Idled Through November
Written by David Schollaert
September 22, 2022
US Steel Corp.’s month-long maintenance outage on the No. 3 blast furnace at Mon Valley Works near Pittsburgh is expected to be completed on Saturday, Sept. 24, a company spokeswoman confirmed to SMU.
Once complete, the blast furnace is expected to remain idle for the next month or so in response to declining demand and market conditions, sources familiar with the matter told SMU.
When asked for comment on the potential idling, US Steel said that “market conditions will dictate if it is restarted.”
The blast furnace was taken offline on Aug. 30—pulled forward by more than a month—for shotcrete (sprayed concrete) reline and maintenance, a significantly shorter and less expensive process than a full reline.
Mon Valley Works has two blast furnaces: No. 1 and No. 3. The No. 1 furnace has a daily ironmaking capacity of approximately 3,200 tons. The No. 3 furnace has a daily capacity of approximately 2,900 tons.
The furnaces are located at US Steel’s Edgar Thomson plant in Braddock, Pa. That facility makes slabs and rails them to the company’s Irvin Plant in West Mifflin, Pa., where they are rolled into sheet.
If the latest idling stands true, this would be the third in a series of idlings this month, following the temporary idling of the No. 5 tin line and the No. 8 blast furnace at Gary Works in Indiana.
The Pittsburgh-based steelmaker has said weaker demand and increased imports were to blame for the two temporary idlings.
The potential idling of No. 3 at Mon Valley Works comes on the back of lower third-quarter earnings guidance—down nearly 50% sequentially and 60% year-on-year—while negotiations for a new labor contract between the steelmaker and the United Steelworkers union seem to be at an impasse, according to a Sept. 16 USW bargaining update.
By David Schollaert, David@SteelMarketUpdate.com

David Schollaert
Read more from David SchollaertLatest in Steel Mills

USW seeks clarity on plans for Granite City Works
The United Steelworkers union has asked U.S. Steel to elaborate on its Granite City Works plans following reports that the steelmaker is ending processing at the facility.

Nucor maintains plate prices, opens October order book
Nucor aims to keep plate prices flat for a seventh straight month with the opening of its October order book.

ArcelorMittal Mexico to import from sister mills as it works to resume DRI production
ArcelorMittal has partially restarted operations at its direct reduction plant in Lazaro Cardenas, Michoacan. An explosion on Aug. 18 rocked the massive steelworks on Mexico’s Pacific coast, impacting production of direct-reduced iron (DRI).

Fall maintenance outages are coming in hot
Labor Day has passed, the sun is starting to set a little earlier each day, and cooler weather has begun to find its way down to many of us across North America. And you know what that means for the steel industry… Fall maintenance outages!

AISI: Domestic steel production ticks up
US raw steel production ticked up in the week ending on Sept. 6 after a decrease the week before, according to the most recent data from the American Iron and Steel Institute (AISI).