SMU Survey: Sheet lead times inch up, plate moves lower
Written by Brett Linton
September 18, 2025
Sheet and plate lead times moved in opposite directions this week, according to SMU’s latest market survey. Sheet times ticked higher but remain within days of multi-year lows, territory they have been in since May. Plate lead times have shifted lower in the past month but remain about a week longer than they were at this time last year.
The average lead time for hot-rolled coil is four and a half weeks. Cold-rolled and coated products are all in the mid-to-upper six-week range. Plate is just over five weeks.
Table 1 summarizes current lead times and recent changes by product (click to expand)

Compared to our early-September market check, two of our lead time ranges shifted this week. The shortest cold rolled and galvanized lead time considered increased from four weeks to five.

Most buyers foresee stability, some expect extensions
Over half of buyers (61%) expect lead times to hold steady through the next two months, in line with our most recent two surveys. Of the remainder, 30% foresee longer lead times in the near future, a rate that has steadily grown across the last few months. The remaining 9% anticipate contractions, similar to previous expectations.
Here are some of the comments we collected:
“Lead times have been very short, mills will start to hold the line in the winter months to start setting up for better Q1 ’26 contract mechanism pricing.”
“I feel in early November we will see more buying as companies replenish some stock for 2026.”
“Remaining too short to really get any buyers nervous.”
“I see them extending in the near term, but eventually normalizing and flattening out.”
“After extending, they will go flat.”
“Sideways, I see little reason for business to pick up much right now.”
Trends
To highlight broader trends, lead times can be calculated on a three-month moving average (3MMA) basis (Figure 2). Three of our four sheet product 3MMAs slightly increased this week, reversing a nine-survey trend of being steady to down. The 3MMA for cold-rolled held stable, while plate edged lower.
Average lead times by product across the last three months were: hot rolled at 4.5 weeks, cold rolled at 6.3 weeks, galvanized at 6.2 weeks, Galvalume at 6.3 weeks, and plate at 5.3 weeks.

Note: These lead times are based on the average from manufacturers and steel service centers participating in this week’s SMU market trends analysis survey. SMU measures lead times as the time it takes from when an order is placed with the mill to when it is processed and ready for shipping, not including delivery time to the buyer. Our lead times do not predict what any individual may get from any specific mill supplier. Consult your mill rep for actual lead times. To see an interactive history of our steel mill lead times data, visit our website. If you’d like to participate in our survey, contact us at info@steelmarketupdate.com.

Brett Linton
Read more from Brett LintonLatest in Features

Final Thoughts
We’ve been talking about a potential inflection point for the past couple of weeks. And the market does appear to be nearing one.

Worthington Steel becomes member of AISI
The American Iron and Steel Institute (AISI) has added Worthington Steel to its membership roster and elected Geoff Gilmore, president and chief executive officer of the steel processor, to its board of directors.

SMU Survey: Mills slightly less negotiable on spot pricing
Sheet and plate buyers say mills remain open to negotiating spot prices this week, though less so than in recent weeks, according to SMU’s latest market survey.

August service center shipments and inventories report
US service centers flat-rolled steel supply in August declined month-over-month (m/m) and year-over-year (y/y), according to SMU data.