Nucor Gallatin's Full Run Rate Pushed Back to Q1’23
Written by David Schollaert
October 20, 2022
Nucor Corp.’s $650 million expansion project at Nucor Steel Gallatin in Ghent, Ky., will not reach its nameplate capacity of 3 million tons per year by the end of the year, Leon Topalian, Nucor’s chair, president, and CEO, said on an earnings conference call with analysts on Thursday, Oct. 20.
“The ramp-up at Nucor Steel Gallatin continues to progress,” he said. “Although we anticipated a full run rate production by the end of this year, we now expect that this will occur in the first quarter of 2023.”
Recall that in June Nucor completed a planned outage at the Gallatin mill related to an expansion that will boost capacity from 1.6 million tons to 3 million tons per year. The company has also expanded the width of the slabs produced at Gallatin from 68 inches to 73.5 inches.
In July, the Charlotte, N.C.-based steelmaker announced the facility had produced the first coil on its upgraded equipment — an 18-mm thick strip, and a new product for the plant.
Ramp-up was expected over the course of the third quarter and hitting its nameplate capacity of 3 million tons per year was planned for the fourth quarter, but that has now been pushed back to Q1 2023.
“The majority of our startup delays have centered around equipment sequencing and remembering that this… was a complete modernization of the entire facility, including new automation software throughout the mill,” said Topalian.
The executive said that Gallatin’s expansion project “dramatically advances the rest of the market solutions” the mill can provide.
Since Nucor’s initial announcement to roughly double Gallatin’s capacity back in 2018, a galvanizing line was added in 2019, and the addition of a pickle line and the tube mill, currently under construction and expected to be operational by mid-2023, “dramatically advance the rest of the market solutions” the Gallatin mill can provide, noted Topalian
“Collectively, these efforts position Gallatin with a higher, more value-added products suite and will enable our team to generate higher profit margins as we move forward,” he added.
The steelmaker previously estimated shipments from Gallatin’s new capacity to reach 500,000 tons this year. The new tube mill at Gallatin will have a 250,000-tons-per-year HSS, mechanical tubing, and galvanized solar torque tube line. The tube mill is expected to be operational by mid-2023.
By David Schollaert, David@SteelMarketUpdate.com

David Schollaert
Read more from David SchollaertLatest in Steel Mills

Steel Summit: Schneider sees SDI ‘on the edge of a very good run’
Steel Dynamics Inc. (SDI) President and Chief Operating Officer, Barry Schneider, remains bullish about the Fort Wayne, Ind.-based steelmaker’s position in the current market.

Steel Summit: Burritt says USS and Nippon are fast-tracking modern steelmaking
U.S. Steel President and CEO David Burritt told audiences at SMU's Steel Summit 2025 that the iconic American steelmaker’s partnership with Nippon Steel is fast-tracking smarter steel production.

Nucor moves to stop HRC price slide with $10/ton hike
Nucor is attempting to halt the decline in hot-rolled coil prices with the announcement of a $10-per-short-ton increase in its weekly consumer spot price on Monday.

Explosion rocks ArcelorMittal’s DR plant in Mexico
ArcelorMittal reported a "strong" explosion at the direct reduction part of its massive Lazaro Cardenas mill in Mexico.

SDI to acquire remaining stake in New Process Steel
Steel Dynamics Inc. (SDI) announced that it has agreed to acquire the remaining 55% equity interest in New Process Steel.