Stelco Holdings Inc. said its fourth-quarter steel shipments were negatively impacted by production challenges and unplanned outages.
The Hamilton, Ontario-based steelmaker shipped roughly 625,000 net tons of steel in the fourth quarter of 2021, below prior guidance of 675,000 to 680,000 net tons.
Shipments in the fourth quarter were lower than expected due to various production challenges, including unplanned outages on its hot strip mill, logistics hurdles, and delays at the end of Q4 brought on by the Omicron variant, the company said.
The negative news didn’t stop there for Stelco. The Canadian steelmaker also provided its first quarter 2022 guidance – and indicated that steel shipments would be similar to or below fourth-quarter totals.
Stelco said the lower guidance for Q1 is a result of planned outages that have been pulled forward in response to its fourth-quarter challenges. Weaker guidance also stems from declining steel prices, weaker demand, and limited labor availability due to increased COVID disruptions, the company said.
By David Schollaert, David@SteelMarketUpdate.com

David Schollaert
Read more from David SchollaertLatest in Steel Mills

AHMSA opens doors to potential buyers as $1.3B asset auction nears
AHMSA is opening its doors to potential buyers to tour its steel plant and mining operations in northern Mexico in preparation for the next stage of its bankruptcy process: the auction of its assets.

USW seeks clarity on USS plans for Granite City Works
The United Steelworkers union has asked U.S. Steel to elaborate on its Granite City Works plans following reports that the steelmaker is ending processing at the facility.

Nucor maintains plate prices, opens October order book
Nucor aims to keep plate prices flat for a seventh straight month with the opening of its October order book.

ArcelorMittal Mexico to import from sister mills as it works to resume DRI production
ArcelorMittal has partially restarted operations at its direct reduction plant in Lazaro Cardenas, Michoacan. An explosion on Aug. 18 rocked the massive steelworks on Mexico’s Pacific coast, impacting production of direct-reduced iron (DRI).

Fall maintenance outages are coming in hot
Labor Day has passed, the sun is starting to set a little earlier each day, and cooler weather has begun to find its way down to many of us across North America. And you know what that means for the steel industry… Fall maintenance outages!