US Steel Corp.’s month-long maintenance outage on the No. 3 blast furnace at Mon Valley Works near Pittsburgh is expected to be completed on Saturday, Sept. 24, a company spokeswoman confirmed to SMU.
Once complete, the blast furnace is expected to remain idle for the next month or so in response to declining demand and market conditions, sources familiar with the matter told SMU.
When asked for comment on the potential idling, US Steel said that “market conditions will dictate if it is restarted.”
The blast furnace was taken offline on Aug. 30—pulled forward by more than a month—for shotcrete (sprayed concrete) reline and maintenance, a significantly shorter and less expensive process than a full reline.
Mon Valley Works has two blast furnaces: No. 1 and No. 3. The No. 1 furnace has a daily ironmaking capacity of approximately 3,200 tons. The No. 3 furnace has a daily capacity of approximately 2,900 tons.
The furnaces are located at US Steel’s Edgar Thomson plant in Braddock, Pa. That facility makes slabs and rails them to the company’s Irvin Plant in West Mifflin, Pa., where they are rolled into sheet.
If the latest idling stands true, this would be the third in a series of idlings this month, following the temporary idling of the No. 5 tin line and the No. 8 blast furnace at Gary Works in Indiana.
The Pittsburgh-based steelmaker has said weaker demand and increased imports were to blame for the two temporary idlings.
The potential idling of No. 3 at Mon Valley Works comes on the back of lower third-quarter earnings guidance—down nearly 50% sequentially and 60% year-on-year—while negotiations for a new labor contract between the steelmaker and the United Steelworkers union seem to be at an impasse, according to a Sept. 16 USW bargaining update.
By David Schollaert, David@SteelMarketUpdate.com

David Schollaert
Read more from David SchollaertLatest in Steel Mills

CMC Q4 profits rise on improved market conditions
CMC reported higher net earnings in its fiscal fourth quarter on "better market conditions" across its segments.

AISI: Raw steel production drops to multi-month low
After being historically strong for more than four months, US raw steel production fell for a second week.

U.S. Steel sues Algoma over iron pellet shipments
U.S. Steel is suing Algoma over the Canadian flat-rolled producer's rejection of iron pellet shipments, arguing it has breached its contract.

August US mill shipments slip but still higher than last year
The American Iron and Steel Institute reported a decline in the monthly shipments of US mills from July to August.

TransPod, Algoma, Supreme Steel linkup anchors Canadian steel in high-speed transit build
The three Canadian companies have announced a strategic partnership to support the development of an ultra-high-speed transit line from Edmonton to Calgary.