NLMK USA has planned a roughly month-long outage for upgrades to its electric-arc furnace (EAF) sheet mill in Portage, Ind.
The work is scheduled for October and November and will be focused on enhancements to the plant’s melt shop and hot strip mill, a company spokesman said.
NLMK USA in emails to customers specified the dates as Oct. 24 through the week of Nov. 20.
“Our contract customers and regular spot buyers are covered throughout these outages,” the spokesman said, noting that the work was planned and scheduled well in advance.
Work on the melt shop will be aimed at improving its reliability. The outage on the hot strip mill is to implement a new automated gauge control (AGC) system, he said.
“That will enable us to hold quarter standard ASTM tolerances throughout our full range of products at Indiana,” the spokesman said.
NLMK USA operates an EAF steel mill in Portage, Ind., a hot strip mill and cold reduction mill in Farrell, Pa., and a galvanizing facility in Sharon, Pa. The Portage mill has a capacity of 800,000 tons per year.
NLMK USA is hardly alone in conducting a fall outage.
US Steel has taken a month-long outage on the No. 3 blast furnace at its Mon Valley Works in western Pennsylvania. The company has also slated a week-long outage at its Big River Steel EAF sheet mill in Arkansas for late October.
And on the plate side, SSAB Americas has moved up a planned outage from October into September.
That list is a not comprehensive but provides some sense of the wave of outages underway or upcoming.
By Michael Cowden, Michael@SteelMarketUpdate.com

Michael Cowden
Read more from Michael CowdenLatest in Steel Mills

Cliffs talks DOE funding, blast furnace relining schedule
The future of two projects supported in part by funding through the Department of Energy remains uncertain.

Cleveland-Cliffs open to asset sales
Meanwhile, its Canadian operations have been hurt by the broader tariffs proposed by the United States.

As Q1 loss balloons, Cliffs pledges to cut costs, streamline operations
Cleveland-Cliffs Inc. gushed red ink in the first quarter, and pledged to stem the bleeding by idling inefficient, “loss-making operations” and increasing focus on its core automotive business.

Cliffs plans to idle three mills, cut 950 jobs on ‘insufficient demand and pricing’
Cleveland-Cliffs plans to indefinitely idle its steel mill in Riverdale, Ill., as well as mills in Conshohocken, Pa., and Steelton, Pa. The Cleveland-based steelmaker said all three facilities would be idled on or around June 30. Approximately 950 jobs will be impacted, the company said.

CRU: Usiminas may reduce capex unless government strengthens protection
“The lack of effective measures to create fair competition, amid a surge in subsidized imports, is the main threat to the sustainability of Brazil’s steel industry and its value chain,” CEO Marcelo Chara said.