NLMK USA is taking an unplanned seven- to 10-day outage on the hot-strip mill at its facility in Farrell, Pa., a company executive said.
The repairs are necessary because a motor failed on the reversing roughing mill, NLMK USA Executive Vice President James Banker told Steel Market Update on Tuesday, May 11.
The company will therefore pull forward planned maintenance on the hot-strip mill that had been scheduled for June. The repairs will result in hot-rolled coil orders being delayed by approximately two weeks, he said.
“We’ll be caught up by June. And we’ll be prioritizing orders that are affected by this outage,” Banker said.
Shipments of downstream pickled-and-oiled (P&O), cold-rolled and coated products should not be impacted because those lines already had work-in-process inventory on hand, he said.
While the June outage on the hot-strip mill has been pulled forward, planned outages on downstream operations remain scheduled for July, Banker said.
The Farrell mill, like NLMK’s electric-arc furnace (EAF) steel mill in Portage, Ind., typically takes one week of downtime for major planned maintenance every six months, he noted.
Also known as NLMK Pennsylvania, the Farrell mill is the company’s largest plant in the U.S. Farrell’s hot-strip mill has annual capacity of 1.8 million tons, according to the Association for Iron and Steel Technology’s 2021 Directory of Iron and Steel plants. NLMK USA sells hot-rolled coil, hot-rolled P&O, cold-rolled coil, and galvanized products to service centers as well as a range of end-use markets, including HVAC, appliance, and pipe and tube.
NLMK’s Sharon Coating facility, located in nearby Sharon, Pa., makes galvanized and galvannealed products.
By Michael Cowden, Michael@SteelMarketUpdate.com

Michael Cowden
Read more from Michael CowdenLatest in Steel Mills

Cliffs talks DOE funding, blast furnace relining schedule
The future of two projects supported in part by funding through the Department of Energy remains uncertain.

Cleveland-Cliffs open to asset sales
Meanwhile, its Canadian operations have been hurt by the broader tariffs proposed by the United States.

As Q1 loss balloons, Cliffs pledges to cut costs, streamline operations
Cleveland-Cliffs Inc. gushed red ink in the first quarter, and pledged to stem the bleeding by idling inefficient, “loss-making operations” and increasing focus on its core automotive business.

Cliffs plans to idle three mills, cut 950 jobs on ‘insufficient demand and pricing’
Cleveland-Cliffs plans to indefinitely idle its steel mill in Riverdale, Ill., as well as mills in Conshohocken, Pa., and Steelton, Pa. The Cleveland-based steelmaker said all three facilities would be idled on or around June 30. Approximately 950 jobs will be impacted, the company said.

CRU: Usiminas may reduce capex unless government strengthens protection
“The lack of effective measures to create fair competition, amid a surge in subsidized imports, is the main threat to the sustainability of Brazil’s steel industry and its value chain,” CEO Marcelo Chara said.