USS Pulls Ahead Planned Maintenance on Mon Valley Blast Furnace
Written by Michael Cowden
July 21, 2022
US Steel plans to take an approximately one-month outage in September on the No. 3 blast furnace at is Mon Valley Works near Pittsburgh, a company spokeswoman said.
The steelmaker plans to apply shotcrete – sprayed concrete – to the furnace, she added.
Shotcrete is a significantly shorter and less expensive process than a full reline.
The work was originally scheduled for mid-October.
Mon Valley Works has two blast furnaces: No. 1 and No. 3. The No. 1 furnace has daily ironmaking capacity of approximately 3,200 tons. The No. 3 furnace has daily capacity of approximately 2,900 tons.
The furnaces are located at US Steel’s Edgar Thomson plant in Braddock, Pa. That facility makes slabs and rails them to the company’s Irvin Plant in West Mifflin, Pa., where they are rolled into sheet.
SMU has updated its blast furnace status table, found by clicking here, to reflect the development.
By Michel Cowden, Michael@SteelMarketUpdate.com

Michael Cowden
Read more from Michael CowdenLatest in Steel Mills

Nucor reports IT systems breach
Nucor said it temporarily and proactively halted some production operations at various locations.

Cliffs talks DOE funding, blast furnace relining schedule
The future of two projects supported in part by funding through the Department of Energy remains uncertain.

Cleveland-Cliffs open to asset sales
Meanwhile, its Canadian operations have been hurt by the broader tariffs proposed by the United States.

As Q1 loss balloons, Cliffs pledges to cut costs, streamline operations
Cleveland-Cliffs Inc. gushed red ink in the first quarter, and pledged to stem the bleeding by idling inefficient, “loss-making operations” and increasing focus on its core automotive business.

Cliffs plans to idle three mills, cut 950 jobs on ‘insufficient demand and pricing’
Cleveland-Cliffs plans to indefinitely idle its steel mill in Riverdale, Ill., as well as mills in Conshohocken, Pa., and Steelton, Pa. The Cleveland-based steelmaker said all three facilities would be idled on or around June 30. Approximately 950 jobs will be impacted, the company said.