• Skip to main content

    Market Data

    Steel Mill Lead Times: Extended at 5-8 Weeks

    Written by Tim Triplett


    Based on the latest SMU Flat Rolled and Plate Steel Market Trends Survey, mill lead times on flat rolled steel remain highly extended, close to the levels measured by Steel Market Update in mid-2016, as mills scramble to fill orders on strong demand. Mill lead times, which are the amount of time it takes for the domestic mills to produce a new order taken this week, is one of the key proprietary indicators tracked by Steel Market Update. Lead times reflect the activity at the mills and the order levels they are seeing from their customers. SMU’s latest data indicates that the average lead time for hot rolled remains at between five and six weeks, while cold rolled, galvanized and Galvalume are at or near an average of eight weeks.

    By product category, hot rolled lead times now average 5.73 weeks, up slightly from 5.65 weeks a month ago. Hot rolled lead times have stretched by more than two weeks since steel prices began rising in October.

    Latest in Market Data

    SMU flat-rolled market survey results now available

    The results of the latest Steel Market Update (SMU) flat-rolled market survey are now available on our website to all premium members. After logging in, look under the Data tab for Market Reports, and there you will find the Flat-Rolled Survey Results section. Previous survey results are also available on that page. If you need help accessing these results, or if your company would like to have your voice heard in our future surveys, contact smu@crugroup.com.

    Lead times extend as HR passes 10 weeks, plate sets another record

    US sheet and plate buyers face longer waits amid historically constrained US steel supply, according to the latest SMU steel market survey data. Average lead times now nearly reach mid-February, with some mills not quoting availability until March or later. For most sheet products—except Galvalume—buyers haven’t faced waits this long since the post-pandemic rebound in 2021. Plate has gone further, surpassing its 2021 peak and repeatedly reaching new highs over the past month. SMU’s plate data stretch back to 2018, and our sheet data to 2012.

    Global steel output holds steady in October, China’s share slips

    Global raw steel production held steady in October, pausing a four-month decline, according to the latest World Steel Association (worldsteel) figures. Output totaled an estimated 142.4 million metric tons (mt), unchanged from September but down 1.2% year over year (y/y). Global production averaged 149.3 million mt per month on a 12-month moving average (12MMA) basis through October. This was down 1.2% y/y and was the lowest 12MMA since 2017 (Figure 1). Before September 2025, the 12MMA of monthly output had generally hovered between 152 million mt and 154 million mt for over three years, similar to pre-pandemic levels.