    Mill Lead Times Extend to Record Lengths

    Written by John Packard


    Flat rolled and plate steel mill lead times continue to extend, according to the results of this week’s flat rolled and plate steel analysis conducted by Steel Market Update. Hot rolled lead times have sustained 10 weeks or more for a month – the first time that has happened in the history of our records, which go back to 2011. We are also seeing record extended lead times on cold rolled, galvanized, Galvalume and plate steels.

    arrow rideHot rolled lead times are now averaging 10.63 weeks, according to the manufacturing companies and service centers participating in this week’s survey. To put this into perspective, the 10.63 weeks is 2.76 weeks longer than what was being reported to SMU at the beginning of January 2021. One year ago, HRC lead times were 7 weeks shorter than what we are reporting today. The historical average HRC lead time (measured prior to the beginning of the current cycle, which began in August 2020) has been 4 weeks (3.98 weeks) based on our past survey data.

    Latest in Market Data

    Final Thoughts: Do Mesabi Metallics and Hyundai-POSCO signal more foreign steel investment in US?

    Could two new steel projects signal a new direction in the marketplace? Both Mesabi Metallics’ recently announced steel facility in Iowa and the Hyundai-POSCO’s proposed mill in Louisiana are major undertakings. You don’t spitball a major steel mill and then start producing the next day. From initial concept to site selection and on up to the first melt, there is a labyrinth of permitting, planning, and construction to navigate before the first heat.

    Lead times extend deeper into 2027, some see no availability until late Feb

    Lead times for sheet and plate products continue to extend in a US steel market still in the grip of a historic supply squeeze, according to the latest SMU steel market survey data. Average lead times now extend into late January 2027, with some mills not quoting availability until mid/late February. Lead times for all sheet products except Galvalume stand at their highest point since the post-Covid demand snapback in 2021. And plate lead times have exceeded their 2021 peak, repeatedly setting new record highs in our data series over the past month. (We started collecting plate lead time data in 2018. Our sheet lead time figures go back to 2012.)

    SMU flat-rolled market survey results now available

    The results of the latest Steel Market Update (SMU) flat-rolled market survey are now available on our website to all premium members. After logging in, look under the Data tab for Market Reports, and there you will find the Flat-Rolled Survey Results section. Previous survey results are also available on that page. If you need help accessing these results, or if your company would like to have your voice heard in our future surveys, contact smu@crugroup.com.

    SMU Survey: Steel mill negotiations remain rare as buyers face tight supply

    Only 5% of steel buyers surveyed by SMU this week said mills were willing to negotiate lower prices for new spot orders, suggesting mills retain substantial pricing leverage in a tight market. The share rose two percentage points from our previous survey two weeks ago but was nine points below the mid-October reading. This week's rate is just slightly higher than our previous survey when the negotiation rate fell to 3% — its lowest level since July 2021. Negotiation rates have trended downward all year as steel prices have continued to climb.